Project 525: Zoom Phone System Replacement

Timeline

  • August 8, 2023: *Early Adopter Migration Phase 1
  • September 13, 2023: *Early Adopter Migration Phase 2
  • October 6, 2023 (extended deadline): Desk phone request due; International calling request due
  • October 13, 2023: Multi-line user form due; Financial Manager/ Business Coordinator review due
  • October 20-31, 2023: Physical desk phone requests reviewed by divisions
  • October 25, 2023: *Early Adopter Migration Phase 3
  • December 15, 2023: Recommended deadline to download voicemails
  • December 19, 2023: Migration for the majority of the Campus Community
  • December ’23 – January ’24: Physical Desk Phone Collection (location list)
  • **March 13, 2024 (this is a date change): Advisor, Fax lines, Analog phones, and final migration of remaining lines

    * Learn more about early adopter phases
    **This date was changed as of 02/29/24 due to vendor problems. The original date was 03/4/24.

Town Halls & Training

  • Town Hall Dates
    • The Town Halls are now complete and were held on October 19 and 24. Here is the slide deck and a web recording of the session.
  • Training

Forms

  • Request to keep a physical desk phone was due Friday, October 6, 2023This form was CLOSED on October 16. New requests can be submitted after the migration on December 19.
    • Additional Niner Insider reminders were sent the week of 9/18 and 9/25.
  • Request International callingwas due Friday, October 6, 2023This form was CLOSED on October 16. New requests can be submitted after the migration on December 19.
    • Targeted emails were sent on 9/7, 9/20, and 9/27
  • Request for multi-linewas due Friday, October 13, 2023This form was CLOSED on October 16. New requests can be submitted after the migration on December 19.
    • Targeted emails were sent on 10/3 and 10/12.

Contact Us

If you have any questions or concerns, please contact the OneIT Service Desk.